The works and progress as per project is itemized below:
Concreting of coral walkways/footpaths around the Halls of residence (In progress to be completed by Dec 2012)
Concreting of coral walkways/footpaths within the HOR blocks (In progress to be completed by Dec 2012)
Installing hand rails to the front steps and ramp of the campus (In progress to be completed by Dec 2012)
Building extensions to two toilets blocks to include disabled toilets and showers (In progress to be completed by Dec 2012)
Build disabled ramp from upper campus to Halls of residence (In progress to be completed by Dec 2012)
Build ramps for wheelchair access to classrooms (In progress to be completed by Dec 2012)
Build ramp from New Law Wing to covered walkway (In progress to be completed by Dec 2012)
Opening up of library entrance. (In progress)
Completion of the Outdoor Study Fale on Tafea Center (10.09.12)
Concreting of Hall of Residence Car Park (complete 02.07.12)
Perimeter back fence (completed 18.07.12)
Finance Office Extension (to start Dec 2012)
Library Fire Alarm (to start Dec 2012)
Installation of 2No. 6,000ltr water tanks at Emalus. (12.08.12) Four 6,000ltr tanks 2No. for Santo Centre and 2No. for Tanna centre ready to be shipped.
Tonga Campus now has a total land area of 19 acres and is located in ‘Atele, in the village of Ha’ateiho, about 7km from Nuku’alofa. Expansion plans are underway for Infrastructure Development Plan on the recent acquired 14 acres.
Projects
Future Plan
Future Extension Plans
Restructuring plans for Tonga Campus are to:
A parameter fence is currently being constructed at the new land at Tonga Campus.
Tuvalu Campus is on Crown Lease Land which has a total land area of 0.2390 acres. This lease expires in 2016.
In 2012, USP Tuvalu Campus successful acquired two additional pieces of land adjoining the campus, one of about 0.1955 acres to the East. The other of about 0.1430 acres to the North. A total of 0.5775 acres will be owned by the University once the agreement is finalized.
Projects
Projects
There were no recent projects in Tuvalu Campus
Future Plan
Future Extension Plans
The Tuvalu Campus expansion projects specifications are:
To resolve the long overdue problem of space shortages faced by Tuvalu Campus there are development plans to accommodate the increase number of students.
Kiribati
Kiribati
Area
Area
Lease Details
Lease Details
Kiribati Campus is on leased land for fifty years commencing from 1 April 2008 to 2033. Lease number is Teabanimate 791 (a). Total land area is 1.779 acres. Kiribati campus is located on Bairiki, Tarawa.
Projects
Projects
There were no recent projects in Kiribati Campus
Future Plan
Future Extension Plans
The Kiribati Campus expansion projects specifications are:
A 3 storey building is currently proposed for Kiribati Campus. Works at the campus will begin in 2013.
Campus Land is Leased by the Education Department for usage by the campus
Projects
Projects
There is no major project for Niue yet.
Future Plan
Future Extension Plans
There is no major future extension plan for Niue yet.
Nauru
Nauru
Area
Area
The total land area is 0.14622 hectares.
Lease Details
Lease Details
Nauru Campus is on leased land for twenty years commencing from 1 April 2000 to 31 March 2020. The total land area is 0.14622 hectares. Lease number is Portion 219 and 220 Aiwo. Nauru Campus is currently located in the Aiwo District.
Projects
Projects
There is no major project for Nauru yet.
Future Plan
Future Extension Plans
There is no major future extension plan for Nauru yet.
Tokelau
Tokelau
Area
Area
Tokelau campus land area is a quarter acre from the year 2000.
Lease Details
Lease Details
Campus is on Leased land by government.
Projects
Projects
There is no major project for Tokelau yet.
Future Plan
Future Extension Plans
There is no major future extension plan for Tokelau yet.
Alafua Campus is on Leased Land of 34 Hectares. Lease Number is Parcel 1254, Part Parcel 439 Flur V Upolu. Lease is from 12/1/1995 to 31 December 2037.
Projects
Projects
There were no major projects in Alafua except for the installation of the new air-condition units at the Campus.
Future Plan
Future Extension Plans
There are no developmental plans confirmed for Alafua Campus yet.
Marshall Islands
Marshall Islands
Area
Area
Lease Details
Lease Details
Campus is on Leased land by government. The total land area is one hectare. Marshall Island Campus is located in the Capital City, Majuro.
Projects
Projects
There were no major projects in Marshall Islands yet
Future Plan
Future Extension Plans
There are no developmental plans confirmed for Marshall Islands yet.